Project TitleProject NumberBid #Submittal Closing Date
4H Memorial Camp Dining and Kitchen Areas Remodeling04O01N/A10/01/2003
Abbott Power Plant - 3rd RO, Supply, Storage, and Waster Water Treatment Systems ImprovementsU10131N/A07/16/2010
Abbott Power Plant - Gas Boiler ReplacementU12145N/A03/01/2012
Abbott Power Plant - Gas Boiler Replacement - Phase 2U14111N/A06/27/2014
Abbott Power Plant - Intake Cooler - EPC Project #004 U15057N/A07/10/2015
Abbott Power Plant - Utilities Production & Distribution Master PlanU10045N/A01/20/2011
Aerodynamics Research Lab AdditionU13017N/A01/08/2013
African American Cultural Center ReplacementU16055N/A06/23/2016
Airport Engineer RetainerU18R19N/A03/30/2017
Airport Planner RetainerU18R20N/A04/07/2017
Allerton 4-H Dining Hall RenovationU07040N/A02/19/2007
Allerton Park and Retreat Center Master PlanA14001N/A03/21/2014
Altgeld Hall - Electrical Service UpgradeU07130N/A10/04/2007
Altgeld Hall and Illini Hall - Renovation Feasibility Study U10047N/A11/10/2009
Altgeld Hall Renovation and Illini Hall ReplacementU19019N/A12/07/2018
Altgeld Hall Renovation and Illini Hall ReplacementU19019N/A04/11/2019
Animal Feed Processing Facility - Feasibility StudyU07022N/A04/02/2007
Applied Life Studies - Feasibility StudyU06029N/A11/04/2005
Architectural RetainerU18R01N/A01/18/2017
Architectural RetainerU20R01N/A07/26/2019
Architectural Retainer - RU20R01-RN/A11/01/2019
Architectural Retainer ContractU09R01N/A01/05/2009
Architectural Retainer ContractU13R02N/A03/23/2012
Architectural Retainer FY14U14R04N/A02/28/2013
Architecture Building - Remodeling and Addition Feasibility StudyU14034N/A11/13/2014
Armory - CITL RenovationU14084N/A09/10/2014
Armory - Classroom RepairsU10084N/A04/08/2010
Armory - Limited Renovation of Restrooms, Windows, Doors and FloorsU08052N/A04/23/2008
Armory - Sprinkler InstallationU08059N/A05/05/2008
Armory Building - South Exterior Envelope & Floors 1 & 2 Office RemodelingU14110N/A04/14/2015
Armory, Foellinger Auditorium, Huff Hall - Life Safety Deficiency CorrectionsU07058N/A04/02/2007
Art & Design Building - Space Consolidation Feasibility StudyU14055N/A01/23/2014
Asbestos & Lead-Based Paint Abatement Retainer ContractU09R02N/A01/05/2009
ASL Basement Remodeling for PGI IGB Interim Facility04C04N/A11/05/2003
Assembly Hall - Renovation and Addition - Master ProjectU11055N/A05/10/2011
Assembly Hall - Structural Investigation and Load RatingU11100N/A07/11/2011
Athletics Maintenance & Operations FacilityU17027N/A01/10/2017
Bevier and Gregory Halls Elevator Improvements0007N/A07/07/2004
Bevier Hall - Elevator ModernizationU09085N/A04/10/2009
Bevier Hall - Infrastructure Renovation - Phase 1U13122N/A06/24/2013
Bevier Hall - Infrastructure Renovation Phase 2U16062N/A10/10/2016
Bevier Hall - Window Replacement
  • Division 01 - General Work
U19032BAU1903210/06/2020
Bielfeldt Athletic Administration Building - Hall of Fame Room RemodelingU13023N/A11/14/2012
Biomass (Miscanthus) CHP and Storage SiloU08098N/A09/18/2008
BSL3 Biocontainment LaboratoryU08097N/A09/10/2008
Burrill Hall - Infrastructure and First Floor RepairsU08075N/A04/25/2008
Burrill Hall - MCB Center for Undergraduate Advising & Instruction U15047N/A03/20/2015
Burrill Hall Electrical UpgradeU06049N/A02/27/2006
Business Instructional Facility - 4th Floor Office AdditionU16102N/A06/15/2016
Business Instructional Facility - Courtyard RenovationsU15048N/A04/20/2015
Business Instructional Facility - Courtyard RenovationsU15048N/A04/20/2015
Campus Chilled Water Conversions - Engineering ServicesU09083N/A03/12/2009
Campus Chilled Water Distribution to Talbot Lab & Grainger LibraryU10034N/A05/03/2011
Campus Controls Upgrades for Setback Scheduling (CDB)U10042N/A01/26/2012
Campus Landscape Master PlanU20070N/A08/26/2020
Campus Master Plan Update Urbana ChampaignA15001N/A04/07/2015
Campus Recreation IMPE Phase 2 - LandscapingU08037N/A01/10/2008
Center for Veterans in Higher Education - Design DevelopmentU11098N/A05/03/2011
CERL Main Building AdditionU13024N/A02/06/2013
Champaign Campus Housing Feasibility Study05C15N/A11/23/2004
Champaign Housing Landscape and LightingU07093N/A10/24/2008
Champaign Housing Redevelopment - Phase IU06018N/A09/19/2005
Chemistry Annex - Addition and RenovationU12238N/A10/26/2012
Chilled Water Extension - Lincoln Hall and Newman CenterU07052N/A03/29/2007
Civil Engineer RetainerU14R06N/A04/03/2013
Civil Engineering Hydrosystems Laboratory - Renovation and ExpansionU15029N/A02/18/2015
Civil Engineering Hydrosystems Laboratory - Renovation and ExpansionU15029N/A04/10/2017
Civil Engineering Hydrosystems Laboratory BP2 - Renovation And Expansion
  • Division 01 - General Work
U15029-2BAU15029-BP205/29/2020
Civil Engineering RetainerU18R11N/A03/03/2017
Civil Engineering Retainer ContractU09R05N/A01/05/2009
Clark Hall 3rd & 4th Floor Remodel04C15N/A01/12/2004
College of Engineering Buildings - EPC Project 03U14076N/A04/04/2014
Conference CenterU06013N/A10/07/2005
Crop Sciences - New Research BuildingU11063N/A05/12/2011
Cultural Centers, Ethnic Studies, and Gender/Women Studies BuildingU11065N/A04/11/2011
Davenport Hall - Exterior RepairsU11082N/A04/21/2011
Davenport Hall - Master PlanU12223N/A06/29/2012
Davenport Hall - West RenovationU18012N/A02/27/2018
David Kinley Hall - Classroom RemodelingU09141N/A06/08/2009
David Kinley Hall - Exterior Door and Window Replacement - Phase 2U13115N/A07/15/2013
David Kinley Hall - HVAC and Electrical Remediation U08100N/A06/30/2008
DCL - Main Electrical Service Replacement and Emergency Lighting UpgradeU12137N/A02/23/2012
Design CenterU16015N/A12/02/2015
DIA-Baseball and Softball Training Centers
  • Division 02 - Plumbing Work
  • Division 03 - Heating, Piping, Refrigeration, and Temperature Control Work
  • Division 04 - Ventilation and Air Distribution Work
  • Division 05 - Electrical Work
U19046BAU1904608/17/2020
DIA-Baseball and Softball Training Centers
  • Division 01 - General Work
U19046BAU1904608/18/2020
DIA-Baseball and Softball Training Centers
  • Division 02 - Plumbing Work
  • Division 03 - Heating, Piping, Refrigeration, and Temperature Control Work
  • Division 04 - Ventilation and Air Distribution Work
  • Division 05 - Electrical Work
U19046BAU19046R11/24/2020
DIA-Baseball and Softball Training Centers
  • Division 01 - General Work
U19046BAU19046R12/04/2020
DIA - Soccer/Track ComplexU18038N/A02/21/2018
DIA - Track and Field ReplacementU18086N/A07/16/2018
Digital Computer Lab 3rd Floor Remodel03N01N/A01/27/2003
Digital Computer Lab CITES Remodel03N12N/A07/14/2004
Digital Computer Laboratory - Life Safety and HVAC UpgradesU18018N/A07/10/2018
Digital Computer Laboratory RemodelU06048N/A02/06/2006
Digital Computing Laboratory - Bioengineering Lab Remodel Phase 2U09031N/A10/08/2008
Digital Computing Laboratory - Bioengineering Lab Remodel Phase 2U13019N/A10/30/2012
Division of Intercollegiate Athletics - Atkins Tennis Center and Eichelberger Field ExpansionU06023N/A10/07/2005
Division of Intercollegiate Athletics - Facility Planning StudyU14015N/A12/16/2013
Dormitory Life Safety Code 2000 Analysis02U01N/A05/08/2002
Education Building - Exterior Repairs and Ground Floor Room Renovations (CDB)U10038N/A12/20/2010
Education Building HVAC Replacement Phase I & IIU07068N/A06/26/2007
Education Building Phase IV Remodeling05CDB08N/A03/09/2005
Electrical and Computer Engineering FacilityU08032N/A01/18/2008
Elevator Consultant Retainer ContractU08R03N/A03/20/2008
Elevator Consultant Retainer ContractU09R07N/A01/05/2009
Engineering Sciences Building - Exterior Repairs to Roofs and WindowsU10137N/A07/20/2010
English Building- Slate Roof ReplacementU16002N/A10/23/2015
English Building - Courtyard Roof Replacement and Chilled Water ConnectionU11073N/A04/21/2011
English Building - Interior and Exterior RepairsU08069N/A04/29/2008
Environmental Management ConsultantU14R01N/A04/23/2013
Environmental Management RetainerU18R18N/A03/14/2017
Everitt Lab Electrical Systems Replacement DesignU07082N/A11/15/2007
Everitt Laboratory Fourth Floor RemodelingU06007N/A08/09/2005
Everitt Laboratory Renovation - Bioengineering Grainger Engineering Breakthroughs InitiativeU14088N/A04/18/2014
Everitt Laboratory Renovation - Bioengineering Grainger Engineering Breakthroughs InitiativeU14088N/A05/01/2014
Everitt Laboratory Renovation - Bioengineering Grainger Engineering Breakthroughs InitiativeU14088N/A07/22/2014
Family Resiliency Building02C08N/A10/11/2002
Family Resiliency Center02C08N/A10/01/2002
FAR Oglesby Traction Elevator ReplacementU08063N/A04/17/2008
FAR Trelease Traction Elevator ReplacementU09097N/A04/07/2009
Field Turf Installation at Stadium Terrace and First StreetU07018N/A01/09/2007
Foellinger Auditorium - Balcony Seating RenovationU13043N/A03/22/2013
Foreign Language Building - Exterior Repairs and HVAC Remediation Phase IIU09114N/A06/18/2009
Foreign Language Building - Life Safety and HVAC RemediationU08047N/A03/14/2008
Fred Turner Student Services Building - Roof Replacement
  • Division 01 - General Work
U19086BAU1908605/07/2020
Freer Hall - Pool Infill RenovationU15043N/A02/16/2015
Freer Hall Install Fire Suppression SystemU06001N/A08/01/2005
Freer Hall Third Floor South Gym RemodelU07046N/A02/28/2007
Fruit Research Farm - Relocation - Phase IIU07126N/A07/26/2007
Gregory Drive Reconstruction - Oak Street to First StreetU12089N/A01/12/2012
Gregory Hall - HVAC ReplacementU08051N/A04/18/2008
Gregory Hall - Interior Repair Plan Phase 2U10090N/A04/12/2010
Gregory Hall Life Safety Deficiency CorrectionsU07056N/A03/26/2007
Henry Administration Building - Envelope Repair & HVAC UpgradeU15038N/A01/07/2015
Henry Administration Building - UOFPPU06015N/A10/11/2005
Henry Administration Building Phase IV - OSAC RemodelU07042N/A02/22/2007
Historic Preservation Architect RetainerU14R02N/A04/19/2013
Historic Preservation Architect RetainerU18R10N/A03/07/2017
Historic Preservation Architect Retainer ContractU09R03N/A01/05/2009
Housing - Goodwin and Green Apartments - Window ReplacementU12233N/A05/23/2012
Housing - ISR - Dining Feasibility StudyU12054N/A01/30/2012
Housing - ISR - Food Service Building - Kitchen Ventilation ReplacementU10097N/A04/29/2010
Housing - ISR - Wardall Hall - Elevator ReplacementU12162N/A04/20/2012
Housing - Life Safety Upgrades at Goodwin and Green Street ApartmentsU10080N/A04/23/2010
Housing - Life Safety Upgrades at LAR - Phase IIU10078N/A04/23/2010
Housing - Life Safety Upgrades at Scott Hall U10081N/A04/23/2010
Housing - Life Safety Upgrades at Taft Van Doren U10079N/A04/23/2010
Housing - Life Safety & Finish Upgrades at Hopkins and Weston HallsU11070N/A03/29/2011
Housing - Life Safety, Finish Upgrades, & A/C Installation at Snyder Hall U11069N/A03/29/2011
Housing - Sprinkler & Finish Work Upgrades at Busey/Evans - Phase IU08057N/A04/08/2008
Housing - Sprinkler & Finish Work Upgrades at PAR - Phase IIU08076N/A04/25/2008
Housing Food Stores - Culinary Kitchen Remodel Phase IIU13061N/A03/25/2013
Housing Food Stores Feasibility StudyU13062N/A03/25/2013
Housing Life Safety Code 2000 - Fire Alarm Upgrade and Highrise Sprinkler - Phase VU07005N/A12/01/2006
Housing Life Safety Code 2000 - Fire Alarm Upgrade & ISR Sprinkler - Phase VIU07124N/A08/28/2007
Housing Life Safety Code 2000 - Sherman Piping Valves Replacement Phase II04C47N/A08/20/2004
Housing Life Safety Code 2000 - Sprinkler & Finish Work Upgrades at PAR - Phase IU07125N/A08/28/2007
Housing Life Safety Code 2000 Fire Alarm Upgrade and Highrise Sprinkler04C46N/A08/18/2004
Huff Hall - North AdditionU08048N/A03/10/2008
Huff Hall - Southeast Classroom and Infrastructure RenovationU12252N/A06/20/2012
IDOT 220 Mph High Speed Rail Preliminary Feasibility StudyU11062N/A03/07/2011
Ikenberry Commons Phase C & D - Residence Hall West and Garner Hall DemolitionU09009N/A10/23/2008
Ikenberry Commons Phase E & G - Residence Hall No. 2 and Forbes Hall DemolitionU09081N/A06/22/2009
Ikenberry Commons #3 Residence Hall with Taft and Van Doren Demo - MasterU12197N/A04/25/2012
Illini Orange Remodel04C16N/A01/09/2004
Illini Union - Facility StudyU16058N/A03/24/2016
Illini Union - Infrastructure RepairsU09036N/A02/20/2009
Illini Union - Infrastructure Repairs - Phase 2U10139N/A07/19/2010
Illini Union - Infrastructure Repairs Phase 2 Feasibility StudyU10067N/A02/01/2010
Illini Union - Remodel Illini Rooms A, B, & CU08023N/A11/02/2007
Illini Union Levis Center - West Exterior Egress TowerU13060N/A03/20/2013
Illinois Autonomous and Connected Track FacilityU20029N/A10/01/2020
Illinois Field - Baseball Locker Room AdditionU09156N/A07/23/2009
Illinois Field - Baseball Training CenterU19046N/A03/14/2019
Illinois Field - Grandstand Improvements and ExpansionU12258N/A07/16/2012
Illinois Fire Service Institute - Burn Site Feasibility StudyU12214N/A05/18/2012
Illinois Fire Service Institute Learning Resource & Research CenterU07087N/A08/28/2007
Illinois Height Modernization Program - Phase 1U09102N/A04/16/2009
Illinois Height Modernization Program - Phase 2 - Master ProjectU10064N/A01/04/2010
Illinois Height Modernization Program - Year 3 - Master ProjectU11038N/A01/04/2011
Illinois Height Modernization Program - Year 4 U12046N/A11/03/2011
Illinois Height Modernization Program - Year 5 - Master ProjectU13008N/A10/25/2012
Illinois Height Modernization RetainerU13R01N/A03/15/2012
Illinois Height Modernization RetainerU14R10N/A04/12/2013
Illinois Height Modernization RetainerU18R16N/A03/17/2017
ILLINOIS STREET RESIDENCE - TOWNSEND AND WARDALL HALLS RENOVATION U18041N/A02/19/2018
ILLINOIS STREET RESIDENCE - TOWNSEND AND WARDALL HALLS RENOVATION U18041N/A06/07/2018
Illinois Street Residence Dining Facility Renovation & AdditionU12054N/A12/09/2016
Illinois Street Residence Halls - Townsend & Wardall Halls Feasibility StudyU14009N/A09/20/2013
Indoor Golf Facility04S17N/A05/05/2004
Integrated Bioprocessing Research LaboratoryU07063N/A04/04/2007
Irwin Academic Services Center Addition05C41N/A04/29/2005
Japan House Addition - Ogura-Sato AnnexU19002N/A11/09/2020
Krannert Art Museum - HVAC RemediationU09033N/A10/28/2008
Krannert Art Museum HVAC Repair DesignU08004N/A01/10/2008
Krannert Center For Performing Arts - Accessibility and Elevator UpgradesU19035N/A08/21/2019
Krannert Center For Performing Arts - Accessibility and Elevator Upgrades
  • Division 05 - Electrical Work
U19035BAU1903511/04/2020
Krannert Center For Performing Arts - Accessibility and Elevator Upgrades
  • Division 01 - General Work
U19035BAU1903511/06/2020
Krannert Center for the Performing Arts - Exterior RenovationsU12231N/A06/26/2012
Laboratory Facilities - EPC Project #005U16061N/A03/03/2016
Landscape Architect RetainerU16R02N/A01/04/2016
Landscape Architect Retainer ContractU08R02N/A03/20/2008
Landscape Architect Retainer ContractU12R01N/A01/12/2011
LAR - Upgrade Kitchen Exhaust & Mechanical SystemsU07006N/A10/20/2006
Law Building - Classroom Revitalization and AdditionU16030N/A03/10/2016
Law Building - Design Concept Feasibility StudyU10036N/A10/08/2009
Library and Undergraduate Library - Life Safety Improvements04S14N/A11/16/2004
Library Remote Storage Phase IIU06069N/A03/27/2006
Lincoln Ave Residence Hall - Fire Suppression System - Phase I U09135N/A06/19/2009
Lincoln Hall04C24N/A02/11/2004
Loomis Laboratory - Instructional Space and Infrastructure RepairsU12163N/A05/14/2012
Loomis Laboratory Ha Lab RemodelingU07003N/A01/09/2007
Main Library - Phase 2 B of the Redevelopment Plan (CDB)U10039N/A01/23/2012
Main Library - Phase 2A of the Redevelopment PlanU10089N/A04/15/2010
Main Library - Rare Book & Manuscript Library - HVAC RemediationU08060N/A04/17/2008
Main Library and Undergraduate Library - Program Assessment and Development PlanU07057N/A04/26/2007
Main Library Feasibility Study05C19N/A12/17/2004
Material Science and Engineering Building First Floor West Wing RemodelU14115N/A06/23/2014
Materials Science and Engineering Building - 212 Suite Laboratory RemodelingU12092N/A02/13/2012
Materials Science and Engineering Building Phase IIA RemodelingU06030N/A11/10/2005
Mech Engineering Bldg CEMMS Clean Room Lab Remodeling04N05N/A12/09/2003
Mechanical Electrical Engineer RetainerU14R08N/A03/11/2013
Mechanical Engineering Building - Renovation and AdditionU12262N/A08/22/2016
Mechanical Engineering Building - Renovation and Addition - ConceptualizationU12262N/A12/04/2012
Mechanical/ Electrical Engineering Retainer ContractU08R04N/A03/21/2008
Mechanical/ Electrical Engineering Retainer ContractU09R06N/A01/05/2009
Mechanical/Electrical Engineer RetainerU18R05N/A01/05/2017
Mechanical/Electrical Engineering Retainer ContactU12R02N/A01/12/2011
Medical Sciences Bldg. - Renovation of Instructional Labs0005N/A09/01/2004
Medical Sciences Building - Carle Illinois College of Medicine RenovationU17077N/A06/13/2017
Medical Sciences Building - Life Safety UpgradesU13051N/A01/24/2013
Medical Sciences Building - Renovation of Instructional Labs (CDB)U10024N/A01/12/2012
Medical Sciences Building - Ventilation RemediationU08070N/A04/29/2008
Memorial Stadium - Masonry Repointing Study U12009N/A09/30/2011
Memorial Stadium - SE Addition & RenovationU17018N/A10/07/2016
Memorial Stadium - SE Addition & RenovationU17018N/A11/03/2016
Memorial Stadium - South and East Facility StudyU14058N/A12/20/2013
Memorial Stadium - Strategic Plan Feasibility Study05S02N/A08/19/2004
Mock Facility Roof Replacement
  • Division 01 - General Work
UXC002BAUXC00204/30/2020
Morrill Hall - Sprinkler & Fire Alarm UpgradesU08061N/A04/28/2008
Morrill Hall AHU ReplacementU07066N/A03/11/2008
Multiple Building - Emergency Masonry Reconstruction (CDB)U19061N/A08/01/2019
Multiple Building - Life Safety UpgradesU16028N/A04/05/2016
Multiple Building - Restroom Renovation Phase II U16021N/A10/09/2015
Multiple Building - Roof ReplacementsU16022N/A10/12/2015
Multiple Building Elevator UpgradesU16019N/A01/27/2016
Multiple Building Restroom Renovations U13034N/A01/08/2013
Multiple Building Roof Replacement FY2019U19024N/A03/21/2019
Multiple Building Roof Replacement FY2019
  • Division 04 - Ventilation and Air Distribution Work
  • Division 05 - Electrical Work
U19024BAU1902409/22/2020
Multiple Building Roof Replacement FY2019
  • Division 01 - General Work
U19024BAU1902409/24/2020
Mumford Hall Electrical Systems ReplacementU07081N/A10/18/2007
Mumford House RestorationU09112N/A04/28/2009
Music Building - Renovate Instructional Labs0006N/A07/21/2004
Natrual Gas Retainer FY 2008U07R02N/A04/09/2007
Natural Gas Engineer RetainerU14R15N/A04/25/2013
Natural Gas Engineer RetainerU18R15N/A04/18/2017
Natural Gas Transmission Pipeline Relocation05S06N/A11/23/2004
Natural History Building - Assessment and Development PlanU06083N/A05/19/2006
Natural History Building - ATLAS Computer LabsU08036N/A01/10/2008
Natural History Building - CMU12063N/A11/17/2011
Natural History Building - ConceptualizationU11007N/A09/23/2010
Natural History Building - Structural AnalysisU09080N/A02/25/2009
Natural History Building Conceptualization and Renovation U13NHBAdU13016N/A09/12/2012
NCSA Petascale Computing Facility - Infrastructure Upgrade for Beyond Blue WatersU16097N/A03/31/2016
NCSA Petascale Computing Facility - Infrastructure Upgrade for Beyond Blue WatersU16097N/A06/06/2016
NCSA Track 1 Data Processing CenterU08012N/A09/17/2007
NCSA Track 1 Data Processing Center ConceptualizationU07071N/A05/01/2007
New Residence Hall - Phase I (Architect of Record)U06018-RH-AORN/A09/11/2006
Newmark Civil Engineering Building - Crane Bay InfillU13113N/A06/26/2013
Newmark Civil Engineering Building - Student Center AdditionU08071N/A04/24/2008
North Campus Parking Deck - College of Engineering Build OutU12049N/A01/11/2012
North Campus Parking Deck - Install Solar Array - Conceptualization U13038N/A01/09/2013
North Campus Parking Deck - USGS Addition and Parking RenovationU12251N/A06/25/2012
Noyes Laboratory - Exterior RepairsU10082N/A03/30/2010
Noyes Laboratory - West Classroom RenovationU15001N/A06/05/2015
Noyes Laboratory Renovation - Nanoscale Theory CenterU13112N/A07/12/2013
Oak Street Chiller Plant - ESCOU11080N/A06/06/2011
Oak Street Chiller Plant & Distribution SystemU08034N/A01/10/2008
Olympic Sports Performance Development & Competition Facility Feasibility StudyU08092N/A06/05/2008
Orchard Downs - Apartment RenovationsU12201N/A04/27/2012
PAR BLAISDELL HALL - PHASE 3 REPLACEMENT OF MECHANICAL ROOM SLAB & UTILITIES
  • Division 02 - Plumbing Work
  • Division 03 - Heating, Piping, Refrigeration, and Temperature Control Work
  • Division 05 - Electrical Work
U20098BAU2009808/25/2020
PAR BLAISDELL HALL - PHASE 3 REPLACEMENT OF MECHANICAL ROOM SLAB & UTILITIES
  • Division 01 - General Work
U20098BAU2009808/27/2020
Parking - Central Campus Parking Structure(s)U16113N/A09/14/2016
Parking C7 & C10 Rehabilitation03C19N/A01/15/2003
Parking Deck on Surface Parking Lot E14 - Feasibility StudyU07016N/A11/20/2006
Parking Decks C7 and C10 - Masonry RepairsU13101N/A05/17/2013
Parking Lot E-14 - Lighting Renovation 2013U13097N/A05/01/2013
Parking Master Plan Update - 2014U14069N/A05/23/2014
Parking Structure Lifecycle Analysis 2009U09157N/A07/30/2009
Pavement Analysis StudyU08002N/A02/07/2008
Penn Ave Res Hall Dining Rooms and Dining Svcs Remodeling04C13N/A01/05/2004
Pennsylvania Avenue Residence Hall - Dining Room and Dining Services RemodelU06076N/A04/03/2006
Pennsylvania Avenue Residence Hall - Window Replacement, Phase II04C48N/A08/16/2004
Pennsylvania Avenue Residence Halls - Restroom Renovation - Phase 1U13144N/A10/16/2013
Pennsylvania Avenue Residence Halls - Restroom Renovations Phase IIU15080N/A06/17/2015
Phase I - Small Project SelectionA20002N/A08/19/2020
Photogrammetry and LiDAR ServicesU20R24N/A01/25/2019
Photogrammetry and LiDAR Services RetainerU14R19N/A09/26/2013
Photogrammetry and LiDAR Services RetainerU16R01N/A07/30/2015
Plant Sciences Laboratory - Roof Replacement
  • Division 05 - Electrical Work
U19115BAU1911505/19/2020
Plant Sciences Laboratory - Roof Replacement
  • Division 01 - General Work
U19115BAU1911505/21/2020
Poultry Research Facility RelocationU06072N/A04/04/2006
Prairie Research Institute Feasibility StudyU15027N/A03/24/2015
Printing Building - Remodeling and Addition for ParkingU12064N/A01/23/2012
PRZM 2.0 Test ProjectU139999N/A02/23/2013
Psychology - Roof ReplacementU12166N/A03/22/2012
Public Safety Building - Feasibility StudyU12186N/A04/09/2012
Qualified Providers Prequalification (Phase I) for Guaranteed Energy Savings Performance ContractsA20002N/A01/30/2020
Rehabilitation Education Center - Infrastructure RepairsU10083N/A03/29/2010
Roger Adams Laboratory Addition - Center for Applied Molecular Sciences - Feasibility StudyU19097N/A09/02/2020
School of Labor & Employment Relations - Classroom AdditionU16107N/A08/17/2016
Scott, Snyder, Weston Hall - Limited Remodel at Gregory and Peabody Dr. - Phase IU08056N/A04/17/2008
Sherman Hall - Elevator Replacement - Phase IU13085N/A04/12/2013
Sixth Street and Stadium Reconstruction u12090N/A01/12/2012
Smith Memorial Hall - Infrastructure and Life Safety Phase 2U15091N/A06/25/2015
Smith Memorial Hall - Infrastructure Repairs U11091N/A04/25/2011
Smith Memorial Hall Replace Air Handling Units - Phase IU06002N/A01/04/2007
Social Work Lease Space Build-Out In ECCC Phase IIU07053N/A04/10/2007
South Campus Chilled Water ImprovementsU06010N/A08/18/2005
South Campus Sanitary Sewer ExtensionU06022N/A10/07/2005
South Campus Sanitary Sewer Extension Phase 2AU07140N/A07/26/2007
South Campus Wind TurbineU06019N/A05/12/2006
South Farms-Cable Rigged Camera System for Field Scale Phenotyping
  • Division 05 - Electrical Work
U20127BAU2012709/16/2020
South Farms-Cable Rigged Camera System for Field Scale Phenotyping
  • Division 01 - General Work
U20127BAU2012709/18/2020
Speech & Hearing Clinic - Lab Renovation (CDB)U10043N/A02/25/2015
Structural Engineer RetainerU14R03N/A03/26/2013
Structural Engineer RetainerU18R08N/A01/12/2017
Structural Engineering Retainer ContractU09R04N/A01/05/2009
Student Dining and Residential Programs BuildingU06018-AORN/A01/31/2006
Surveying Building RenovationU14072N/A07/10/2014
Talbot Laboratory - Educational Laboratory Upgrade & ExpansionU15037N/A10/05/2015
The Campus Institute00C501N/A12/28/2000
Trelease Hall and FAR Dining Hall - HVAC, Piping, and Exhaust System UpgradesU16114N/A08/25/2016
Turner Hall - Classroom RenovationsU15026N/A03/24/2015
Turner Hall - Exterior Envelope and Energy ReductionU11071N/A01/31/2012
Turner Hall Crop Sciences and Soils Lab RemodelU12184N/A06/08/2012
Ubben Basketball Complex Expansion U20034N/A10/31/2019
Ubben Basketball Complex Expansion U20034N/A02/20/2020
UIUC and UIS MEP Condition AssessmentU12151N/A02/14/2012
Undergraduate Library RedevelopmentU20118N/A11/12/2020
University High School - Feasibility StudyU08103N/A07/24/2008
University of Illinois Urbana-Champaign Data Processing Center ConceptualizationU07064N/A05/01/2007
Urbana Champaign Big Broadband - Infrastruction InstallationU11008N/A09/17/2010
Utility Engineer RetainerU14R13N/A04/01/2013
Utility Engineer RetainerU18R13N/A02/16/2017
Utility Engineer RetainerU18R13N/A03/27/2017
Utility Engineer RetainerU18R21N/A08/07/2017
Utility Engineering Retainer ContractU12R03N/A01/12/2011
Utility Systems Engineering Retainer ContractU08R01N/A03/20/2008
Vet Med Large Animal Clinic - Renovation (CDB)U10033N/A01/23/2012
Veterinary Medicine Feasibility Study04S19N/A04/30/2004
Veterinary Medicine Large Animal Clinic Remodel Wards 3&4 - Feasibility StudyU07044N/A03/14/2007
Veterinary Teaching Hospital - Small Animal Surgery Renovation & ExpansionU17041N/A06/14/2017
Veterinary Teaching Hospital - Standing Seam Roof ReplacementU14056N/A04/11/2014
Willard Airport - New Traffic Control Tower05O01N/A04/15/2005
Willard Airport Master PlanA06001N/A02/01/2006
Wohlers Hall Life Safety Upgrades and Rm 141 RenovationU18007N/A04/03/2019
Wohlers Hall Life Safety Upgrades and Rm 141 Renovation
  • Division 05 - Electrical Work
  • Division 06 - Sprinkler Work
U18007BAU1800711/10/2020
Wohlers Hall Life Safety Upgrades and Rm 141 Renovation
  • Division 01 - General Work
U18007BAU1800711/12/2020
Wright Street Bike Path - Feasibility StudyU08045N/A03/17/2008