AE Solicitation Worksheet
PUBLIC NOTICE OF CONSTRUCTION RELATED PROFESSIONAL SERVICES
Original Offer Date: 04/17/2007

The Board of Trustees of the University of Illinois hereby requests qualifications from professional services consultants to provide professional services in connection with the following project:
Project Name: NCSA Track 1 Data Processing Center Conceptualization
Description of Project: This will be an all new building of approximately 80,000 gross square feet comprised of 4,000 square feet of offices, 9,000 square feet of storage and loading docks, 20,000 square feet of water cooled data processing machine rooms and 47,000 square feet of data processing machine room support. The facility is projected to require 36MW of electrical power and 4,000 tons of cooling; both redundant feeds from campus utilities. The facility size is to be verified by a room requirements study as part of the program verification. An analysis and recommendations of the chosen site is also part of the project definition study.
Project Area: GSF:0NASF:0
Project Budget: $150,000.00Construction Budget: $0.00

Note: The project will be administered using the Owner's web-based project management system. PRZM was developed to maximaize the potential of the Internet in allowing project team members to access and exchange project information. PRZM supports team colllaboration in management and interaction, as well as a team member empowerment on a multi-layer security system.

Minimum user requirements are as follows:

  • Internet Browser: Microsoft Internet Explorer version 4.0 or higher is recommended.
  • E-mail: PRZM requires the user to have a valid e-mail account.
  • Computer-Aided Drawing (CAD) viewer.

Only those firms which meet the following qualifications will be considered for selection:

  • Licensed to practice as an (Architect, Engineer, or Landscape Architect) in the State of Illinois.
  • Prequalified with the State of Illinois Capital Development Board.
  • Registered and authorized to do business in the State of Illinois.
  • Utilization of AutoCAD compatible System.

The following project-related criteria will be used to evaluate the firms requesting consideration for selection:
  • Current commitments of proposed staff and firm at the University of Illinois
  • Overall design quality of the projects submitted
  • Prior experience with projects at the University/ College level
  • Overall qualifications of the proposed team of individuals and consultants
  • Prior experience with project of similar scope, size and level of complexity
  • MAFBE participation

Firms should submit one electronic copy of their complete submittal response (in pdf format) by 05/01/2007 using the submit button below:

Download an electronic copy of the 255.

Division of Facilities and Services
1501 S. Oak St.
Champaign, IL 61820
Jill A. Maxey, jmaxey@uiuc.edu
The Professional Services Consultant selection will be consistent with the Architectual, Engineering, and Land Surveying Qualifications Based Selection Act (30 ILCS 535/1).

Interested firms should not forward brochures or other data until notified by Division of Facilities and Services.